Production runs get delayed when brands aren't fully prepared at run time. The most common causes: a missing COA, a spec sheet that hasn't been submitted, film that arrives the day before the run instead of a week before. This checklist exists so none of those happen to you.

Phase 1 — Before You Contact a Co-Packer

Have these ready before your first inquiry:

  • Finalized formula — your formula should be locked before you engage a co-packer. Changing your formula after you've ordered film and ingredients is expensive. If you're still developing, develop first.
  • Target fill weight — in grams, per serving. This is the single most important spec for a co-packer. Know this number.
  • Target pouch format — sachet, zipper pouch, or gusset bag. If you're unsure, say so — but have a direction.
  • Target run volume — how many pouches in your first order.
  • Target timeline — when do you need finished goods in hand.

Phase 2 — After You've Chosen a Co-Packer

Documentation

  • Signed MSA (Master Service Agreement) — required before scheduling at Overgang. Don't wait until the week of your run to review and return the MSA.
  • Allergen declaration — a written declaration of all allergens in your product. Required before production. Non-negotiable.
  • Spec sheet / blending instructions — total pounds of blend needed, percentage formulation for each ingredient (must add to 100%), and any specific blending sequence or requirements.
  • Lot number format — how you want lot numbers formatted on your product (example: OVG-2025-07-001).
  • Expiration date — your target expiration date or shelf life calculation (manufactured date + X months).

Film and Packaging

  • Film supplier identified — you need a roll stock film supplier. Overgang does not supply film. We can recommend suppliers we trust.
  • Die lines obtained — request die line templates from your film supplier for your pouch dimensions.
  • Artwork completed and approved by film supplier — artwork approval is required before your film goes into production.
  • Film ordered at 110% of target pouch count — account for yield loss.
  • Film delivery confirmed to arrive at Overgang before run date — with tracking. Late film = late run.

Ingredients

  • Ingredients ordered at 110% of expected output — account for 5–10% yield loss depending on run size.
  • COAs requested from every ingredient supplier — one COA per ingredient, per lot number. Must match the lot you're shipping.
  • COAs reviewed — verify that all tests pass and lot numbers match your ingredient packaging.
  • COAs sent to co-packer at least one week before run date — don't wait until the day of.
  • Ingredients ordered to arrive at Overgang before run date — with tracking. Materials must be on-site before your run is confirmed.

Phase 3 — Week Before Your Run

  • Confirm film has arrived at Overgang — email or call to confirm receipt.
  • Confirm ingredients have arrived at Overgang — confirm receipt of all ingredient lots.
  • Confirm COAs are on file and approved — co-packer should confirm COAs have been received and verified.
  • Confirm run date and time — get written confirmation of your scheduled production date.
  • Provide outbound shipping instructions — where should finished goods ship, what carrier, any special requirements.

Phase 4 — After Your Run

  • Verify finished pouch count — compare to expected output accounting for yield loss.
  • Verify lot numbers and expiration dates — confirm they match your specifications.
  • Request batch records if needed — for compliance documentation purposes.
  • Arrange pickup or confirm outbound shipping — coordinate with your co-packer on finished goods disposition.
  • Note lessons for next run — did materials arrive with enough lead time? Were there formula issues? Build on what you learned.

The #1 cause of run delays

Late film. Film has a 10–12 business day production lead time after artwork approval. Brands who start the film process the same week they want to schedule a run are going to be disappointed. Start the film process 6–8 weeks before your target finished goods date and you'll never have this problem.

Quick Reference Checklist

ItemWhenStatus
Formula finalizedBefore contacting co-packer[ ]
MSA signedBefore scheduling[ ]
Allergen declaration submittedBefore scheduling[ ]
Spec sheet submittedBefore scheduling[ ]
Lot number format specifiedBefore scheduling[ ]
Film supplier identified6–8 weeks before run[ ]
Die lines obtained6 weeks before run[ ]
Artwork approved5 weeks before run[ ]
Film ordered (110%)5 weeks before run[ ]
Ingredients ordered (110%)3–4 weeks before run[ ]
COAs requestedWith ingredient order[ ]
COAs sent to co-packer1+ week before run[ ]
Film confirmed on-site1 week before run[ ]
Ingredients confirmed on-site1 week before run[ ]
Run date confirmed1 week before run[ ]